Substation Scout

Woodward EHV substation interconnection queue

5 active projects totaling 1,017.6 MW in the SPP queue, plus 3 with terminal status (shown grayed).

8 SPP queue filings name Woodward EHV as the point of interconnection, all in OK.

5active projects
1,017.6active MW
8total filed
Queue IDProjectkVMWResourceStatus
GEN-2007-062 Not reported 345 424 Wind Operational
GEN-2008-029 Not reported 138 250.5 Wind Withdrawn
GEN-2011-019 Not reported 345 175 Wind Active
GEN-2011-020 Not reported 345 165.6 Wind Active
GEN-2007-050 Not reported 138 151.8 Wind Operational
GEN-2008-003 Not reported 138 101.2 Wind Operational
GEN-2021-SR6 Not reported 345 80 Battery Withdrawn
GEN-2021-SR7 Not reported 345 20 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first