Substation Scout

SPP request GEN-2007-050

SPP queue ID GEN-2007-050

Queue request GEN-2007-050 was listed in the SPP interconnection queue at the end of 2025 as a 151.8 MW wind project in Woodward County, OK, according to Berkeley Lab’s queue data file. The filing names Woodward EHV as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 23, 2010.

Queue IDGEN-2007-050
Project nameNot reported
Status (as published)Operational
SubstationWoodward EHV
Point of interconnectionWoodward EHV 138kV
CountyWoodward
StateOK
Voltage138 kV
Capacity151.8 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2010-12-23
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Woodward EHV substation: 8 requests in the SPP queue, 5 active totaling 1,017.6 MW.

Queue IDProjectMWResourceStatus
GEN-2007-062Not reported424WindOperational
GEN-2011-019Not reported175WindActive
GEN-2011-020Not reported165.6WindActive
GEN-2008-003Not reported101.2WindOperational
GEN-2008-029Not reported250.5WindWithdrawn
GEN-2021-SR6Not reported80BatteryWithdrawn
GEN-2021-SR7Not reported20BatteryWithdrawn

Woodward, OK: 40 requests in the SPP queue, 13 active totaling 2,028.4 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityOGE
ClusterICS-2008-001-6; 04 SOUTHEAST
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue date2007-10-22
Operational date2010-12-23

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first