1 active project totaling 80 MW in the SPP queue, plus 1 with terminal status (shown grayed).

2 SPP queue filings name Norton as the point of interconnection, all in Quay County, NM.

1active projects
80active MW
2total filed
Queue IDProjectkVMWResourceStatus
GEN-2023-GR3 Not reported 115 80 Wind Operational
GEN-2014-066 Not reported 115 30 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.