Substation Scout

SPP request GEN-2024-SR12

SPP queue ID GEN-2024-SR12

Queue request GEN-2024-SR12 was listed in the SPP interconnection queue at the end of 2025 as a 20 MW battery project in Lamoure County, ND, according to Berkeley Lab’s queue data file. The filing names Edgeley Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 1, 2026.

Queue IDGEN-2024-SR12
Project nameNot reported
Status (as published)Active
SubstationEdgeley Substation
Point of interconnectionEdgeley 115 kV Substation
CountyLamoure
StateND
Voltage115 kV
Capacity20 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2026-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Lamoure, ND: 5 requests in the SPP queue, 1 active totaling 20 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityWAPA
ClusterSurplus; 01 NORTH
Interconnection serviceERIS
Project typeSurplus
Study phase (standardized by Berkeley Lab)IA Pending
Study phase (as the queue printed it)IA PENDING
Queue date2024-05-21

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner