Substation Scout

SPP request GEN-2024-320

SPP queue ID GEN-2024-320

Queue request GEN-2024-320 was listed in the SPP interconnection queue at the end of 2025 as a 199 MW battery project in Wyandotte County, KS, according to Berkeley Lab’s queue data file. The filing names Jaggard Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 15, 2028.

Queue IDGEN-2024-320
Project nameNot reported
Status (as published)Active
SubstationJaggard Substation
Point of interconnectionJaggard 115 kV Substation
CountyWyandotte
StateKS
Voltage115 kV
Capacity199 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2028-12-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Wyandotte, KS: 7 requests in the SPP queue, 5 active totaling 918 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityWERE
ClusterDISIS-2024-001; 03 CENTRAL
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)System Impact Study
Study phase (as the queue printed it)DISIS STAGE
Queue date2025-03-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first