Wyandotte, KS interconnection queue

5 active projects totaling 918 MW in the SPP queue, plus 2 with terminal status (shown grayed).

5active projects
918active MW
7total filed
Queue IDProjectkVMWResourceStatus
GEN-2023-023 Not reported 161 200 Battery Withdrawn
GEN-2023-037 Not reported 161 200 Battery Active
GEN-2024-319 Not reported 161 199 Battery Active
GEN-2024-320 Not reported 115 199 Battery Active
ERAS-2025-029 Not reported 161 170 Battery Active
ERAS-2025-031 Not reported 161 150 Other Active
GEN-2018-062 Not reported 161 75.6 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.