SPP request GEN-2024-289

SPP queue ID GEN-2024-289

Queue request GEN-2024-289 was listed in the SPP interconnection queue at the end of 2025 as a 350 MW solar project in Henry County, MO, according to Berkeley Lab’s queue data file. The filing names Archie - Clinton Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2029.

Queue IDGEN-2024-289
Project nameNot reported
Status (as published)Active
SubstationArchie - Clinton Line
Point of interconnectionArchie - Clinton 161 kV Line
CountyHenry
StateMO
Voltage161 kV
Capacity350 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2029-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Henry, MO: 7 requests in the SPP queue, 4 active totaling 1,300 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityWERE
ClusterDISIS-2024-001; 03 CENTRAL
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)System Impact Study
Study phase (as the queue printed it)DISIS STAGE
Queue date2025-03-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.