SPP request GEN-2024-272
SPP queue ID GEN-2024-272
Queue request GEN-2024-272 was listed in the SPP interconnection queue at the end of 2025 as a 199 MW hybrid project in Pratt County, KS, according to Berkeley Lab’s queue data file. The filing names Sawyer Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 15, 2029.
| Queue ID | GEN-2024-272 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Sawyer Substation |
| Point of interconnection | Sawyer 115 kV Substation |
| County | Pratt |
| State | KS |
| Voltage | 115 kV |
| Capacity | 199 MW |
| Resource (as published) | Solar+Battery |
| Resource category | Hybrid (normalized for filtering) |
| Proposed online date | 2029-12-15 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Pratt, KS: 15 requests in the SPP queue, 6 active totaling 1,104 MW.
Tracked changes
Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | SUNC |
|---|---|
| Cluster | DISIS-2024-001; 03 CENTRAL |
| Interconnection service | NRIS/ERIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | System Impact Study |
| Study phase (as the queue printed it) | DISIS STAGE |
| Queue date | 2025-03-01 |
| Components (hybrid) | Solar 199 MW + Battery |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.