Queue request GEN-2024-231 was listed in the SPP interconnection queue at the end of 2025 as a 65 MW hybrid project in Richardson County, NE, according to Berkeley Lab’s queue data file. The filing names S1399 5 Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 1, 2029.

Queue IDGEN-2024-231
Project nameNot reported
Status (as published)Active
SubstationS1399 5 Substation
Point of interconnectionS1399 5 161 kV Substation
CountyRichardson
StateNE
Voltage161 kV
Capacity65 MW
Resource (as published)Solar+Wind
Resource categoryHybrid (normalized for filtering)
Proposed online date2029-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Richardson, NE: 5 requests in the SPP queue, 2 active totaling 125 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityOPPD
ClusterDISIS-2024-001; 02 NEBRASKA
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)System Impact Study
Study phase (as the queue printed it)DISIS STAGE
Queue date2025-03-01
Components (hybrid)Solar 65 MW + Wind

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.