Substation Scout

SPP request GEN-2024-219

SPP queue ID GEN-2024-219

Queue request GEN-2024-219 was listed in the SPP interconnection queue at the end of 2025 as a 160 MW hybrid project in Murray County, OK, according to Berkeley Lab’s queue data file. The filing names Chigley - Oaklawn Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 28, 2030.

Queue IDGEN-2024-219
Project nameNot reported
Status (as published)Active
SubstationChigley - Oaklawn Line
Point of interconnectionChigley - Oaklawn 138 kV Line
CountyMurray
StateOK
Voltage138 kV
Capacity160 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2030-06-28
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Murray, OK: 13 requests in the SPP queue, 5 active totaling 742.5 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityOGE
ClusterDISIS-2024-001; 04 SOUTHEAST
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)System Impact Study
Study phase (as the queue printed it)DISIS STAGE
Queue date2025-03-01
Components (hybrid)Solar 160 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first