Substation Scout

SPP request GEN-2024-215

SPP queue ID GEN-2024-215

Queue request GEN-2024-215 was listed in the SPP interconnection queue at the end of 2025 as a 300 MW hybrid project in Cloud County, KS, according to Berkeley Lab’s queue data file. The filing names Elm Creek Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 2, 2029.

Queue IDGEN-2024-215
Project nameNot reported
Status (as published)Active
SubstationElm Creek Substation
Point of interconnectionElm Creek 345 kV Substation
CountyCloud
StateKS
Voltage345 kV
Capacity300 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2029-10-02
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cloud, KS: 12 requests in the SPP queue, 7 active totaling 1,430.1 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITCGP
ClusterDISIS-2024-001; 03 CENTRAL
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)System Impact Study
Study phase (as the queue printed it)DISIS STAGE
Queue date2025-03-01
Components (hybrid)Solar 300 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first