Substation Scout

SPP request GEN-2024-184

SPP queue ID GEN-2024-184

Queue request GEN-2024-184 was listed in the SPP interconnection queue at the end of 2025 as a 199 MW battery project in Atoka County, OK, according to Berkeley Lab’s queue data file. The filing names Atoka to Lehigh Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of January 15, 2029.

Queue IDGEN-2024-184
Project nameNot reported
Status (as published)Active
SubstationAtoka to Lehigh Line
Point of interconnectionAtoka to Lehigh 138 kV Line
CountyAtoka
StateOK
Voltage138 kV
Capacity199 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2029-01-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Atoka, OK: 5 requests in the SPP queue, 3 active totaling 599 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAEP
ClusterDISIS-2024-001; 04 SOUTHEAST
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)System Impact Study
Study phase (as the queue printed it)DISIS STAGE
Queue date2025-03-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first