SPP queue ID GEN-2024-089

Queue request GEN-2024-089 was listed in the SPP interconnection queue at the end of 2025 as a 195 MW wind project in Curry County, NM, according to Berkeley Lab’s queue data file. The filing names Pleasant Hills Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 1, 2029.

Queue IDGEN-2024-089
Project nameNot reported
Status (as published)Active
SubstationPleasant Hills Substation
Point of interconnectionPleasant Hills 230 kV Substation
CountyCurry
StateNM
Voltage230 kV
Capacity195 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2029-12-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Curry, NM: 20 requests in the SPP queue, 3 active totaling 695 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySPS
ClusterDISIS-2024-001; 05 SOUTHWEST
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)System Impact Study
Study phase (as the queue printed it)DISIS STAGE
Queue date2024-10-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first