SPP queue ID GEN-2024-058

Queue request GEN-2024-058 was listed in the SPP interconnection queue at the end of 2025 as a 200 MW wind project in Nowata County, OK, according to Berkeley Lab’s queue data file. The filing names Farmland - Delaware line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 29, 2028.

Queue IDGEN-2024-058
Project nameNot reported
Status (as published)Active
SubstationFarmland - Delaware line
Point of interconnectionFarmland - Delaware 138 kV line
CountyNowata
StateOK
Voltage138 kV
Capacity200 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2028-12-29
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Nowata, OK: 11 requests in the SPP queue, 5 active totaling 1,535 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAEP
ClusterDISIS-2024-001; 04 SOUTHEAST
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)System Impact Study
Study phase (as the queue printed it)DISIS STAGE
Queue date2024-10-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first