Nowata, OK interconnection queue
5 active projects totaling 1,535 MW in the SPP queue, plus 6 with terminal status (shown grayed).
5active projects
1,535active MW
11total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2024-345 | Not reported | 345 | 600 | Wind | Active |
| GEN-2024-240 | Not reported | 345 | 300 | Wind | Active |
| GEN-2022-092 | Not reported | 345 | 299.2 | Wind | Withdrawn |
| GEN-2024-060 | Not reported | 345 | 250 | Wind | Withdrawn |
| GEN-2024-346 | Not reported | 138 | 220 | Wind | Active |
| GEN-2022-176 | Not reported | 345 | 215 | Wind | Active |
| GEN-2009-047 | Not reported | 345 | 200 | Wind | Withdrawn |
| GEN-2023-075 | Not reported | 345 | 200 | Wind | Withdrawn |
| GEN-2024-058 | Not reported | 138 | 200 | Wind | Active |
| GEN-2024-208 | Not reported | 138 | 195 | Solar | Withdrawn |
| GEN-2023-076 | Not reported | 345 | 100 | Wind | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.