Queue request GEN-2024-030 was listed in the SPP interconnection queue at the end of 2025 as a 150 MW solar project in Gray County, KS, according to Berkeley Lab’s queue data file. The filing names Santa Fe Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2028.

Queue IDGEN-2024-030
Project nameNot reported
Status (as published)Active
SubstationSanta Fe Substation
Point of interconnectionSanta Fe 115 kV Substation
CountyGray
StateKS
Voltage115 kV
Capacity150 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2028-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Gray, KS: 12 requests in the SPP queue, 4 active totaling 545.6 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySUNC
ClusterDISIS-2024-001; 03 CENTRAL
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)System Impact Study
Study phase (as the queue printed it)DISIS STAGE
Queue date2024-10-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.