Substation Scout

Gray, KS interconnection queue

4 active projects totaling 545.6 MW in the SPP queue, plus 8 with terminal status (shown grayed).

4active projects
545.6active MW
12total filed
Queue IDProjectkVMWResourceStatus
GEN-2022-203 Not reported 345 200 Solar Withdrawn
GEN-2024-093 Not reported 115 180 Solar Withdrawn
GEN-2010-009 Not reported 345 165.6 Wind Operational
GEN-2024-030 Not reported 115 150 Solar Active
GEN-2024-097 Not reported 115 150 Wind Withdrawn
GEN-2007-040 Not reported 345 131.1 Wind Operational
GEN-2012-013 Not reported 115 99 Wind Withdrawn
GEN-2008-079 Not reported 115 98.9 Wind Operational
GEN-2019-079 Not reported 115 13 Wind Withdrawn
GEN-2011-003 Not reported 115 10 Solar Withdrawn
GEN-2015-026 Not reported 345 8.3 Wind Withdrawn
GEN-2015-027 Not reported 115 4.9 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.