Queue request GEN-2023-SR20 was listed in the SPP interconnection queue at the end of 2025 as a 120 MW battery project in Custer County, OK, according to Berkeley Lab’s queue data file. The filing names Weatherford Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2025.

Queue IDGEN-2023-SR20
Project nameNot reported
Status (as published)Active
SubstationWeatherford Substation
Point of interconnectionWeatherford 138 kV Substation
CountyCuster
StateOK
Voltage138 kV
Capacity120 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2025-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Custer, OK: 10 requests in the SPP queue, 4 active totaling 276.8 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAEP
ClusterSurplus; 04 SOUTHEAST
Interconnection serviceERIS
Project typeSurplus
Study phase (standardized by Berkeley Lab)IA Pending
Study phase (as the queue printed it)IA PENDING
Queue date2023-06-21
Operational date2025-06-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first