Queue request GEN-2023-205 was listed in the SPP interconnection queue at the end of 2025 as a 180 MW solar project in Hughes County, OK, according to Berkeley Lab’s queue data file. The filing names McAlester City - Weleetka line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2028.
| Queue ID | GEN-2023-205 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | McAlester City - Weleetka line |
| Point of interconnection | McAlester City - Weleetka 138 kV line |
| County | Hughes |
| State | OK |
| Voltage | 138 kV |
| Capacity | 180 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2028-12-31 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Hughes, OK: 4 requests in the SPP queue, 1 active totaling 180 MW.
Tracked changes
Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | AEP |
|---|---|
| Cluster | DISIS-2023-001; 04 SOUTHEAST |
| Interconnection service | NRIS/ERIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | Facility Study |
| Study phase (as the queue printed it) | FACILITY STUDY STAGE |
| Queue date | 2023-10-02 |