SPP request GEN-2023-199
SPP queue ID GEN-2023-199
Queue request GEN-2023-199 was listed in the SPP interconnection queue at the end of 2025 as a 250 MW hybrid project in Dakota County, NE, according to Berkeley Lab’s queue data file. The filing names Twin Church Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of March 28, 2027.
| Queue ID | GEN-2023-199 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Twin Church Substation |
| Point of interconnection | Twin Church 230 kV Substation |
| County | Dakota |
| State | NE |
| Voltage | 230 kV |
| Capacity | 250 MW |
| Resource (as published) | Solar+Battery |
| Resource category | Hybrid (normalized for filtering) |
| Proposed online date | 2027-03-28 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Twin Church Substation substation: 2 requests in the SPP queue, 2 active totaling 360 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| GEN-2024-162 | Not reported | 110 | Hybrid | Active |
Dakota, NE: 2 requests in the SPP queue, 2 active totaling 360 MW.
Tracked changes
Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | NPPD |
|---|---|
| Cluster | DISIS-2023-001; 02 NEBRASKA |
| Interconnection service | NRIS/ERIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | Facility Study |
| Study phase (as the queue printed it) | FACILITY STUDY STAGE |
| Queue date | 2023-10-02 |
| Components (hybrid) | Solar 250 MW + Battery |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.