Queue request GEN-2023-092 was listed in the SPP interconnection queue at the end of 2025 as a 125 MW hybrid project in Choctaw County, OK, according to Berkeley Lab’s queue data file. The filing names Unger - Frogville line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 30, 2028.
| Queue ID | GEN-2023-092 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Unger - Frogville line |
| Point of interconnection | Unger - Frogville 138 kV line |
| County | Choctaw |
| State | OK |
| Voltage | 138 kV |
| Capacity | 125 MW |
| Resource (as published) | Solar+Battery |
| Resource category | Hybrid (normalized for filtering) |
| Proposed online date | 2028-09-30 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Choctaw, OK: 13 requests in the SPP queue, 6 active totaling 978.8 MW.
Tracked changes
Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | WFEC |
|---|---|
| Cluster | DISIS-2023-001; 04 SOUTHEAST |
| Interconnection service | NRIS/ERIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | Facility Study |
| Study phase (as the queue printed it) | FACILITY STUDY STAGE |
| Queue date | 2023-10-02 |
| Components (hybrid) | Solar 125 MW + Battery |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.