Queue request GEN-2021-057 was listed in the SPP interconnection queue at the end of 2025 as a 300 MW wind project in Antelope County, NE, according to Berkeley Lab’s queue data file. The filing names Antelope substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2027.

Queue IDGEN-2021-057
Project nameNot reported
Status (as published)Active
SubstationAntelope substation
Point of interconnectionAntelope 345kV substation
CountyAntelope
StateNE
Voltage345 kV
Capacity300 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2027-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Antelope, NE: 15 requests in the SPP queue, 7 active totaling 1,123.7 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNPPD
ClusterDISIS-2021-001; 02 NEBRASKA
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Facility Study
Study phase (as the queue printed it)FACILITY STUDY STAGE
Queue date2021-04-29

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.