Queue request GEN-2020-091 was listed in the SPP interconnection queue at the end of 2025 as a 150 MW solar project in Mckenzie County, ND, according to Berkeley Lab’s queue data file. The filing names Patent Gate Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 29, 2029.
| Queue ID | GEN-2020-091 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Patent Gate Substation |
| Point of interconnection | Patent Gate Substation 345 kV |
| County | Mckenzie |
| State | ND |
| Voltage | 345 kV |
| Capacity | 150 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2029-12-29 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Mckenzie, ND: 4 requests in the SPP queue, 2 active totaling 195 MW.
Tracked changes
Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | BEPC |
|---|---|
| Cluster | DISIS-2020-001; 01 NORTH |
| Interconnection service | NRIS/ERIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | IA FULLY EXECUTED/ON SCHEDULE |
| Queue date | 2020-04-30 |