Substation Scout

SPP request GEN-2020-090

SPP queue ID GEN-2020-090

Queue request GEN-2020-090 was listed in the SPP interconnection queue at the end of 2025 as a 204.3 MW battery project in Bourbon County, KS, according to Berkeley Lab’s queue data file. The filing names Wolf Creek - Blackberry Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 1, 2026.

Queue IDGEN-2020-090
Project nameNot reported
Status (as published)Active
SubstationWolf Creek - Blackberry Substation
Point of interconnectionWolf Creek - Blackberry 345 kV Substation
CountyBourbon
StateKS
Voltage345 kV
Capacity204.3 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2026-12-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Bourbon, KS: 7 requests in the SPP queue, 6 active totaling 1,224.3 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNEETSW
ClusterDISIS-2020-001; 03 CENTRAL
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Facility Study
Study phase (as the queue printed it)FACILITY STUDY STAGE
Queue date2020-04-27

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first