SPP request GEN-2020-084
SPP queue ID GEN-2020-084
Queue request GEN-2020-084 was listed in the SPP interconnection queue at the end of 2025 as a 350 MW solar project in Burt County, NE, according to Berkeley Lab’s queue data file. The filing names Raun - Fort Calhoun as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of February 15, 2030.
| Queue ID | GEN-2020-084 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Raun - Fort Calhoun |
| Point of interconnection | Raun - Fort Calhoun 345 kV |
| County | Burt |
| State | NE |
| Voltage | 345 kV |
| Capacity | 350 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2030-02-15 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Burt, NE: 8 requests in the SPP queue, 4 active totaling 1,125 MW.
Tracked changes
Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | OPPD |
|---|---|
| Cluster | DISIS-2020-001; 02 NEBRASKA |
| Interconnection service | NRIS/ERIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | IA FULLY EXECUTED/ON SCHEDULE |
| Queue date | 2020-04-30 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.