Queue request GEN-2020-061 was listed in the SPP interconnection queue at the end of 2025 as a 29 MW gas project in Cass County, MO, according to Berkeley Lab’s queue data file. The filing names Pleasant Hill 345/161/ Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 23, 2026.

Queue IDGEN-2020-061
Project nameNot reported
Status (as published)Active
SubstationPleasant Hill 345/161/ Substation
Point of interconnectionPleasant Hill 345/161/69 kV Substation
CountyCass
StateMO
Voltage69 kV
Capacity29 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2026-10-23
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cass, MO: 11 requests in the SPP queue, 3 active totaling 381 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityGMO
ClusterDISIS-2020-001; 03 CENTRAL
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/ON SCHEDULE
Queue date2020-04-28

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.