Queue request GEN-2019-065 was listed in the SPP interconnection queue at the end of 2025 as a 180 MW battery project in Smith County, TX, according to Berkeley Lab’s queue data file. The filing names Overton-Northwest Henderson as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 1, 2026.

Queue IDGEN-2019-065
Project nameNot reported
Status (as published)Active
SubstationOverton-Northwest Henderson
Point of interconnectionOverton-Northwest Henderson 138kV
CountySmith
StateTX
Voltage138 kV
Capacity180 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2026-12-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Smith, TX: 1 request in the SPP queue, 1 active totaling 180 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAEP
ClusterDISIS-2019-001; 04 SOUTHEAST
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Pending
Study phase (as the queue printed it)IA PENDING
Queue date2019-05-23

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first