SPP queue ID GEN-2019-009

Queue request GEN-2019-009 was listed in the SPP interconnection queue at the end of 2025 as a 100 MW solar project in Nemaha County, NE, according to Berkeley Lab’s queue data file. The filing names S1263 Brock substation as its point of interconnection. Its status as of December 31, 2025 was “Suspended”, with a proposed online date of November 1, 2029.

Queue IDGEN-2019-009
Project nameNot reported
Status (as published)Suspended
SubstationS1263 Brock substation
Point of interconnectionS1263 Brock 161kV substation
CountyNemaha
StateNE
Voltage161 kV
Capacity100 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2029-11-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Nemaha, NE: 6 requests in the SPP queue, 4 active totaling 824 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityOPPD
ClusterDISIS-2019-001; 02 NEBRASKA
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Suspended
Study phase (as the queue printed it)IA FULLY EXECUTED/ON SUSPENSION
Queue date2019-04-24

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.