Queue request GEN-2018-043 was listed in the SPP interconnection queue at the end of 2025 as a 500 MW solar project in Burt County, NE, according to Berkeley Lab’s queue data file. The filing names Ft. Calhoun - Raun Line Break as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 15, 2028.

Queue IDGEN-2018-043
Project nameNot reported
Status (as published)Active
SubstationFt. Calhoun - Raun Line Break
Point of interconnectionFt. Calhoun - Raun 345 kV Line Break
CountyBurt
StateNE
Voltage345 kV
Capacity500 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2028-12-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Burt, NE: 8 requests in the SPP queue, 4 active totaling 1,125 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityOPPD
ClusterDISIS-2018-001; 02 NEBRASKA
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/ON SCHEDULE
Queue date2018-05-29

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first