Queue request GEN-2017-047 was listed in the SPP interconnection queue at the end of 2025 as a 102 MW wind project in Beaver County, OK, according to Berkeley Lab’s queue data file. The filing names Bull Creek substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 16, 2024.

Queue IDGEN-2017-047
Project nameNot reported
Status (as published)Operational
SubstationBull Creek substation
Point of interconnectionBull Creek 115 kV substation
CountyBeaver
StateOK
Voltage115 kV
Capacity102 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2024-12-16
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Beaver, OK: 20 requests in the SPP queue, 8 active totaling 1,676.2 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySPS
ClusterDISIS-2017-001; 05 SOUTHWEST
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue date2017-05-18
Operational date2024-12-27

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first