SPP request GEN-2017-023

SPP queue ID GEN-2017-023

Queue request GEN-2017-023 was listed in the SPP interconnection queue at the end of 2025 as a 85 MW solar project in Choctaw County, OK, according to Berkeley Lab’s queue data file. The filing names Hugo Power Plant Sub as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of March 31, 2026.

Queue IDGEN-2017-023
Project nameNot reported
Status (as published)Active
SubstationHugo Power Plant Sub
Point of interconnectionHugo Power Plant 138 kV Sub
CountyChoctaw
StateOK
Voltage138 kV
Capacity85 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2026-03-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Choctaw, OK: 13 requests in the SPP queue, 6 active totaling 978.8 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityWFEC
ClusterDISIS-2017-001; 04 SOUTHEAST
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/ON SCHEDULE
Queue date2017-05-31

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first