Substation Scout

SPP request GEN-2016-147

SPP queue ID GEN-2016-147

Queue request GEN-2016-147 was listed in the SPP interconnection queue at the end of 2025 as a 40 MW solar project in Cheyenne County, NE, according to Berkeley Lab’s queue data file. The filing names Sidney Sub as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 28, 2024.

Queue IDGEN-2016-147
Project nameNot reported
Status (as published)Active
SubstationSidney Sub
Point of interconnectionSidney 115 kV Sub
CountyCheyenne
StateNE
Voltage115 kV
Capacity40 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2024-06-28
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cheyenne, NE: 8 requests in the SPP queue, 1 active totaling 40 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityTri-State
ClusterDISIS-2016-002-1; 02 NEBRASKA
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/ON SCHEDULE
Queue date2016-11-30
Operational date2024-06-28

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner