Queue request GEN-2011-056 was listed in the SPP interconnection queue at the end of 2025 as a 3.6 MW hydro project in Dawson County, NE, according to Berkeley Lab’s queue data file. The filing names Jeffrey as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of October 31, 2012.

Queue IDGEN-2011-056
Project nameNot reported
Status (as published)Operational
SubstationJeffrey
Point of interconnectionJeffrey 115kV
CountyDawson
StateNE
Voltage115 kV
Capacity3.6 MW
Resource (as published)Hydro
Resource categoryHydro (normalized for filtering)
Proposed online date2012-10-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Dawson, NE: 7 requests in the SPP queue, 3 active totaling 11.7 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNPPD
ClusterDISIS-2011-002-6; 02 NEBRASKA
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue date2011-09-30
Operational date2012-10-31

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first