SPP request GEN-2001-024

SPP queue ID GEN-2001-024

Queue request GEN-2001-024 was listed in the SPP interconnection queue at the end of 2025 as a 630 MW gas project in Washington County, AR, according to Berkeley Lab’s queue data file. The filing names SWEPCO Tontitown Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of July 1, 2007.

Queue IDGEN-2001-024
Project nameNot reported
Status (as published)Operational
SubstationSWEPCO Tontitown Substation
Point of interconnectionSWEPCO Tontitown 161kV Substation
CountyWashington
StateAR
Voltage161 kV
Capacity630 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2007-07-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Washington, AR: 4 requests in the SPP queue, 1 active totaling 630 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAEP
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue date2001-07-09
Operational date2007-07-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.