Substation Scout

Washington, AR interconnection queue

1 active project totaling 630 MW in the SPP queue, plus 3 with terminal status (shown grayed).

1active projects
630active MW
4total filed
Queue IDProjectkVMWResourceStatus
GEN-2001-024 Not reported 161 630 Gas Operational
GEN-2006-007 Not reported n/r 530 Gas Withdrawn
GEN-2009-006 Not reported 161 60 Wind Withdrawn
GEN-2016-166 Not reported 69 35 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first