Queue request ERAS-2025-035 was listed in the SPP interconnection queue at the end of 2025 as a 138 MW gas project in Brown County, SD, according to Berkeley Lab’s queue data file. The filing names Siebrecht Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2029.

Queue IDERAS-2025-035
Project nameNot reported
Status (as published)Active
SubstationSiebrecht Substation
Point of interconnectionSiebrecht 115 kV Substation
CountyBrown
StateSD
Voltage115 kV
Capacity138 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2029-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Brown, SD: 3 requests in the SPP queue, 2 active totaling 408 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNWPS
ClusterERAS-2025-001; 01 NORTH
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)ERAS
Queue date2025-10-02

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.