Substation Scout

Brown, SD interconnection queue

2 active projects totaling 408 MW in the SPP queue, plus 1 with terminal status (shown grayed).

2active projects
408active MW
3total filed
Queue IDProjectkVMWResourceStatus
GEN-2024-035 Not reported 345 270 Hybrid Active
ERAS-2025-035 Not reported 115 138 Gas Active
GEN-2023-084 Not reported 115 100 Hybrid Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first