Substation Scout

Pottawatomie, KS interconnection queue

2 active projects totaling 922.8 MW in the SPP queue, plus 1 with terminal status (shown grayed).

2active projects
922.8active MW
3total filed
Queue IDProjectkVMWResourceStatus
GEN-2007-023 Not reported n/r 800 Coal Withdrawn
GEN-2024-249 Not reported 345 721.2 Gas Active
GEN-2021-107 Not reported 345 201.6 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first