Substation Scout

Pittsburg, OK interconnection queue

5 active projects totaling 1,799.8 MW in the SPP queue, plus 9 with terminal status (shown grayed).

5active projects
1,799.8active MW
14total filed
Queue IDProjectkVMWResourceStatus
GEN-2024-341 Not reported 345 1,045 Gas Active
GEN-2000-007 Not reported n/r 560 Gas Withdrawn
GEN-2001-022 Not reported n/r 550 Gas Withdrawn
GEN-2024-290 Not reported 345 250 Wind Withdrawn
GEN-2024-291 Not reported 345 250 Wind Active
GEN-2017-156 Not reported 345 234 Wind Withdrawn
GEN-2018-082 Not reported 345 215 Wind Active
GEN-2022-196 Not reported 345 215 Wind Withdrawn
GEN-2023-053 Not reported 345 212 Wind Withdrawn
GEN-2017-157 Not reported 345 202 Wind Withdrawn
GEN-2021-065 Not reported 138 200 Hybrid Withdrawn
GEN-2024-250 Not reported 345 199 Battery Active
GEN-2021-066 Not reported 138 150 Hybrid Withdrawn
GEN-2022-071 Not reported 138 90.8 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first