Grant, KS interconnection queue
3 active projects totaling 539.2 MW in the SPP queue, plus 3 with terminal status (shown grayed).
3active projects
539.2active MW
6total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2021-023 | Not reported | 345 | 306.2 | Solar | Active |
| GEN-2023-175 | Not reported | 115 | 200 | Battery | Withdrawn |
| GEN-2012-007 | Not reported | 115 | 120 | Gas | Operational |
| GEN-2021-035 | Not reported | 115 | 113 | Solar | Active |
| GEN-2017-110 | Not reported | 115 | 100 | Solar | Withdrawn |
| GEN-2014-045 | Not reported | 115 | 50 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.