Clay, MO interconnection queue

6 active projects totaling 1,150 MW in the SPP queue, plus 2 with terminal status (shown grayed).

6active projects
1,150active MW
8total filed
Queue IDProjectkVMWResourceStatus
GEN-2022-073 Not reported 161 300 Battery Active
GEN-2024-370 Not reported 161 250 Battery Active
GEN-2022-142 Not reported 161 200 Battery Active
GEN-2023-033 Not reported 161 200 Battery Active
GEN-2023-169 Not reported 161 125 Battery Withdrawn
GEN-2022-102 Not reported 161 100 Battery Active
GEN-2024-090 Not reported 161 100 Battery Active
GEN-2022-125 Not reported 161 75 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.