Clay, MO interconnection queue
6 active projects totaling 1,150 MW in the SPP queue, plus 2 with terminal status (shown grayed).
6active projects
1,150active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2022-073 | Not reported | 161 | 300 | Battery | Active |
| GEN-2024-370 | Not reported | 161 | 250 | Battery | Active |
| GEN-2022-142 | Not reported | 161 | 200 | Battery | Active |
| GEN-2023-033 | Not reported | 161 | 200 | Battery | Active |
| GEN-2023-169 | Not reported | 161 | 125 | Battery | Withdrawn |
| GEN-2022-102 | Not reported | 161 | 100 | Battery | Active |
| GEN-2024-090 | Not reported | 161 | 100 | Battery | Active |
| GEN-2022-125 | Not reported | 161 | 75 | Battery | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.