Southern Company request IC-903

Southern Company queue ID IC-903

Queue request IC-903 was listed in the Southern Company interconnection queue at the end of 2025 as a 13 MW hybrid project in Liberty County, GA, according to Berkeley Lab’s queue data file. The filing names Fort Stewart CU Bus as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 1, 2023.

Queue IDIC-903
Project nameNot reported
Status (as published)Active
SubstationFort Stewart CU Bus
Point of interconnectionFort Stewart CU 115 kV Bus
CountyLiberty
StateGA
Voltage115 kV
Capacity13 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2023-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Liberty, GA: 5 requests in the Southern Company queue, 3 active totaling 192.3 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2020-08-27
Components (hybrid)Solar 13 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first