Queue request 25-IC-1375 was listed in the Southern Company interconnection queue at the end of 2025 as a 325 MW battery project in Jackson County, GA, according to Berkeley Lab’s queue data file. The filing names Center Primary - Pond Fork Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of July 30, 2031.

Queue ID25-IC-1375
Project nameNot reported
Status (as published)Active
SubstationCenter Primary - Pond Fork Line
Point of interconnectionCenter Primary - Pond Fork 230 kV Line
CountyJackson
StateGA
Voltage230 kV
Capacity325 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2031-07-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Jackson, GA: 9 requests in the Southern Company queue, 1 active totaling 325 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Queue date2025-04-17

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first