Substation Scout

Lee, AL interconnection queue

5 active projects totaling 1,208 MW in the Southern Company queue, plus 11 with terminal status (shown grayed).

5active projects
1,208active MW
16total filed
Queue IDProjectkVMWResourceStatus
IC-252 Not reported 230 968 Gas Withdrawn
IC-224 Not reported 230 666.7 Gas Withdrawn
IC-203 Not reported 230 655 Gas Withdrawn
IC-1218 Not reported 230 640 Gas Withdrawn
IC-104 Not reported 500 630 Gas Withdrawn
IC-210 Not reported 230 630 Gas Withdrawn
IC-214 Franklin 3 (Goat Rock 3) n/r 620 Gas Operational
IC-065 Not reported 230 610 Gas Withdrawn
IC-202 Not reported 230 595 Gas Withdrawn
IC-251 Not reported 230 520 Gas Withdrawn
25-IC-1320A Not reported 230 240 Gas Active
IC-1251 Not reported 115 157 Solar Suspended
25-IC-1321 Not reported 230 111 Gas Active
IC-1052 Not reported 115 80 Hybrid Suspended
IC-523 Not reported 115 62.5 Solar Withdrawn
IC-1058 Not reported 115 50 Hybrid Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.