Spurlock-Zimmer 345kV

PJM queue ID Z2-061 Terminal status

Queue IDZ2-061
Project nameSpurlock-Zimmer 345kV
Status (as published)Withdrawn
SubstationSpurlock-Zimmer
Point of interconnectionSpurlock-Zimmer 345kV
CountyMason
StateKY
Voltage345 kV
Capacity88 MW
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operationNot reported
Source datasetserial

Additional filed fields

Project TypeMerchant Transmission
Mfo88
Withdrawn Date4/1/2014

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.