Substation Scout

Dan's Mountain Solar Project

PJM queue ID Z2-038 Terminal status

Queue IDZ2-038
Project nameDan's Mountain Solar Project
Status (as published)Withdrawn
SubstationRidgeley-Frostburg
Point of interconnectionRidgeley-Frostburg 138kV
CountyAllegany
StateMD
Voltage138 kV
Capacity7.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2018-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.9
Mw Capacity7.6
Mfo19.9
Withdrawn Date12/22/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.