Substation Scout

Bay Shore 138kV

PJM queue ID Z1-030 Terminal status

Queue IDZ1-030
Project nameBay Shore 138kV
Status (as published)Withdrawn
SubstationBay Shore
Point of interconnectionBay Shore 138kV
CountyLucas
StateOH
Voltage138 kV
Capacity464 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2017-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy464
Mw Capacity464
Mfo464
Withdrawn Date4/1/2014

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.