Substation Scout

Hanna-Juniper 345kV

PJM queue ID Z1-016 Terminal status

Queue IDZ1-016
Project nameHanna-Juniper 345kV
Status (as published)Withdrawn
SubstationHanna-Juniper
Point of interconnectionHanna-Juniper 345kV
CountyPortage
StateOH
Voltage345 kV
Capacity140 MW
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operationNot reported
Source datasetserial

Additional filed fields

Project TypeMerchant Transmission
Mfo140
Withdrawn Date6/13/2013

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.