Substation Scout

BL England 138kV

PJM queue ID Y2-110 Terminal status

Queue IDY2-110
Project nameBL England 138kV
Status (as published)Withdrawn
SubstationBL England
Point of interconnectionBL England 138kV
CountyCape May
StateNJ
Voltage138 kV
Capacity40 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2016-01-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy40
Mw Capacity40
Mfo565
Withdrawn Date3/7/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.