Easton-Easton Tap 69kV

PJM queue ID Y2-093 Terminal status

Queue IDY2-093
Project nameEaston-Easton Tap 69kV
Status (as published)Withdrawn
SubstationEaston-Easton Tap
Point of interconnectionEaston-Easton Tap 69kV
CountyNorthampton
StatePA
Voltage69 kV
Capacity63 MW
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operation2013-06-01
Source datasetserial

Additional filed fields

Project TypeMerchant Transmission
Mfo63
Withdrawn Date12/7/2012

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.